Motivated
by traffic congestion on the High Level Bridge and stoppages caused by
frequent openings of the Swing Bridge, the contract for this road bridge
was awarded to Dorman, Long & Co of Middlesborough according to specifications
prepared by the engineers Mott, Hay and Anderson.
It is often
believed that the Tyne Bridge was the model for the Sydney Harbour Bridge
but in fact it is actually a scaled-down version of that bridge, which
Dorman Long were already working on.
The Sydney harbour Bridge has a span over three time longer at 1650 feet
The confusion
arises due to the fact that the Tyne Bridge was completed
nearly three years ahead of the Sydney Harbour Bridge.

The Tyne Bridge - The arch nearing completion. 22.2.1928
with Swing Bridge in foreground.
The arch
was constructed out from each bank by the use of cranes, without obstructing
the river.
The arch steelwork during construction was tied back by cables until the
two sides met,
and was finally closed on 25th Feb. 1928.
At the time
of its opening, the bridge was the largest single-span bridge in Britain.
The span is 531 feet and 3500 tons of steelwork were used.
The bridge,
which carries traffic 93 feet above the river, has become the icon of
Newcastle,
and is enhanced by two pairs of granite towers at each end. These were
designed to be
warehouses with five floors but these were never constructed. They also
contained
goods and passenger lifts connecting to the quayside below but are no
longer in use.
The bridge
was painted green with a specially developed paint by J.Dampney &
Co. Gateshead
and the colour was faithfully reproduced during the bridge repaint of
2000.

The Tyne
Bridge was officially opened by King George V on 10th.Oct. 1928
Total cost
of the bridge was £1,200,000

 
©
Doug-on-the-Tyne - 2004
|